Thursday, September 22, 2011

BREAKING NEWS -- TBM Breaks Through


Second Avenue Subway TBM Drills Through Wall
into Lexington Avenue/63rd Street Station

Moments ago, at 11:28 a.m., the tunnel boring machine that had been mining the east tunnel of the Second Avenue Subway reached its final destination. It successfully broke through a rock cavern wall, into open air, deep inside the Lexington Avenue/63rd Street station.



Here you can see the rear wall being watered down, to minimize airborne particles in anticipation of the imminent breakthrough of the TBM.

As the machine's cutterhead broke through the rock cavern wall the assembled crowd cheered loudly to celebrate the momentous occasion.

I was fortunate to witness this historic event -- more than 80 years in the making. A full report, with plenty of pictures, will be posted this evening. Stay tuned.


Update 9/22/11
A full report from the TBM Breakthrough event
can be found on this link:

Subway Infrastructure Milestone Achieved
The Launch Box
9/22/11

Tuesday, September 13, 2011

Brilliant Morning Light on Second Avenue


As we turn the calendar from August to September, we know that summer is nearing an end. As the days get shorter, the shadows along Second Avenue are only getting longer. Still, the brilliant morning light enhances the many bright colors found throughout the work site.

On a recent Friday morning, I set out as early as I could bear in order to capture the ongoing construction work, and the shadows of the rising sun over the active work site.

The MTA's contractors on Second Avenue start work at 7 a.m. I arrived shortly thereafter, and this is what I saw through the lens of my camera.



9/2/11
97th Street - looking S

Workers at this location are in the process of excavating a section of slurry wall trench using the machine shown in this image. The trench will be excavated to a depth of about 100 feet.



9/2/11
btw. 96th and 97 streets - looking NE

Another view of the same machine - in which you can clearly see the hole where the trench is being excavated.

The yellow hose in the foreground is used to deliver a slurry mixture into the trench as they dig. The slurry, which is a mixture of clay and water, keeps the walls of the trench from collapsing.



9/2/11
btw. 95th & 96th streets - looking NE

Once the trench has been excavated, a 100-foot long rebar cage, like the one shown above, will be carefully lowered into the hole.



9/2/11
just south of 96th street - in front of the Rite Aid - looking NE

After that, workers will lower a long tremie pipe into the newly dug trench. Fresh concrete will be poured into the pipe so that the trench can be filled with concrete - from the bottom up. As the concrete rises, the slurry mixture is pumped out so that it can be recycled and used again.



9/2/11
on 95th Street, about 100 feet to the west of 2nd Avenue - looking E

At other locations on the job site, workers were in the process of assembling new rebar cages.

Workers in the image above are just about to start building a new cage on top of the wooden frame shown in this image.

Note the worker (with his protective helmet) who will soon start welding sections of rebar together at this location.



9/2/11
just south of 97th Street - looking NW

Workers in this image are wrapping sections of rebar using heavy steel wire. Basically they are wrapping the sections together so that they don't move when the cage is lifted and lowered into the trench.



9/2/11
btw. 95th & 96th streets - looking E

At a different location on the site, a second machine can be seen excavating another section of slurry wall trench.



9/2/11
87th Street - looking SW

At this location, workers are excavating an access shaft that will be used during the construction of the new 86th Street station. The excavation here is being performed using a technique known as controlled blasting.

Even though the blasts are controlled, they are still quite loud.



9/2/11
btw. 86th & 87th streets - looking W

Another view of the same shaft site. In the lower right corner of the image, you can see a rock drill (which was incredibly loud) boring holes into the bedrock. The explosive charges will be lowered into these holes.



9/2/11

A closer view of the rock drill. If you enlarge this image and look very closely, you can see that the workers are, of course, wearing ear protection.



9/2/11
83rd Street, just to the east of 2nd Avenue - looking W

A view of the site where the other 86th Street station access shaft is being built.



9/2/11
83rd Street - looking E

Another view of the same shaft location, from a different angle.



9/2/11
73rd Street, NE corner

On the left in this image, you can see a environmental monitoring station. At this location, the contractor appears to be monitoring both the sound level and the quality of the air.



9/2/11
79th Street, NE corner - looking SW

Workers at this location, in the middle of Second Avenue, are operating a pumping station that is being used to deliver concrete down into the west tunnel below. The concrete is being used to line the walls of the new tunnel.



9/2/11
69th Street - looking N

A view of the MTA's Muck House between 69th and 72nd street on Second Avenue.

This nondescript temporary structure houses a set of electric winches and skips that are being used to transport muck from the station cavern below to waiting dump trucks at street level.

An identical structure, which can be seen in the distance in this image, has also been put up between 72nd & 73rd streets.

The workers on top of the structure appear to be installing sound insulating material under the roof.



9/2/11

Another view of the work taking place on the roof.

Note the reflections of bright sunlight on the building and the muck house, above and below.



9/2/11

A closer view of the insulation being installed under the roof line.



9/2/11
69th Street - looking N

A view into the muck structure at this location, through the south entrance.

The workers here are lowering a [red] box of supplies(?) into the shaft.



9/2/11
70th Street - looking W

A large section of ventilation pipe is carefully walked down the street.



9/2/11
72nd Street - looking N

A view into the muck structure at this location, through the south entrance. The orange device in the foreground is a mobile ventilation fan.

Workers in this image are lowering one of the skips down into the access shaft.



9/2/11
73rd Street - looking S

A view into the muck structure at this location, through the north entrance.

If you look carefully, you can see rock and other material (i.e. muck) being dropped into the waiting dump truck. The worker on the ladder would appear to be checking to see that they don't load too much material into the truck.



9/2/11

A sign posted on an entrance to the muck house.



9/2/11
72nd Street, NE corner - looking N

A view of the deep cavern that now exists between the muck house and the residential building on the right.

One could assume that the exterior walls of the muck houses have been painted an off-white color so as to reflect as much natural light as possible into this corridor.



9/2/11
73rd Street - looking S

A view of a dump truck that has just entered the structure so that it can be loaded.



9/2/11
73rd Street

This hand-made sign announces the final performance [on Second Avenue] of Gary Russo, the now famous singing ironworker.

At last count, his original video has been viewed by over one million people on YouTube.



9/2/11
63rd Street, btw. Lexington & 3rd - looking E

At this location, on the north side of the street, workers are excavating part of the plaza so that they can access the existing station below.



9/2/11
63rd Street & 3rd Avenue, SW corner - looking S

A survey team at work, at 7:10 a.m.



9/2/11
Existing Lexington Avenue/63rd Street station
Track 1 - Southbound
Looking W

Passengers waiting for a southbound F train.

This station is in the process of being completely renovated as part of the project. The renovation includes the activation of a set of long dormant tracks on the other side of the orange wall, and the opening of four new station entrances on 3rd Avenue.


::


A Note About the Current Location
of the Tunnel Boring Machine (TBM):


As of 7 a.m. on Tuesday morning (9/13/11), the TBM was 296 linear feet away from its final destination: the lower level of the stub cavern at the Lexington Avenue/63rd Street station. This would put it somewhere near the middle of the city block that is bordered by 63rd & 64th streets and 3rd & Lexington avenues.

With good rock (i.e. rock without fractures, so they can mine 50 to 70 feet a day) they most likely will [now] break through into the stub cavern sometime early next week.

Please stand by for further news...

Update - 9/20/11
As of 7 a.m. today the TBM had just 77 feet left to mine.


:::::


Off Topic:
The Tenth Anniversary of 9/11

I know that this is off-topic, but I felt compelled to include a few links here to mark the passing of the tenth anniversary of 9/11.

The four pieces that I selected, all from The New York Times, highlight the men and women who are working to rebuild the World Trade Center site.

"The Workers"
By Fred Conrad, Nick Harbaugh and Andrea Rice
The New York Times - 9/8/11
"The World Trade Center site employs more than 3,200 workers. At present, it is the largest construction project in the United States. These portraits [146 in total] and audio narratives are a testament to their myriad skills and talents."

"Ironworkers of the Sky"
By Randy Kennedy
The New York Times - 9/4/11

"Raising High Steel Atop 1 World Trade Center"
By Damon Winter
The New York Times - 9/4/11
Eleven black-and-white photographs by the Damon Winter, a Pulitzer Prize-winning photographer for the newspaper.

"Reaching the Heights"
By Dean Robinson
The New York Times - 9/2/11
A behind-the-scenes look at how Damon Winter got his pictures from the top of 1 World Trade Center.

Friday, September 2, 2011

TBM NEARS END OF RUN


Second Avenue Tunnel Boring Machine (TBM)
Nears the End of its Second Run


Breakthrough into Existing Lexington Avenue/
63rd Street Station Just Weeks Away


Recently released data indicates that the TBM working under Second Avenue is now about 500 feet away from its final stop, the Lexington Avenue/63rd Street station.

Based on its current rate of progress, it could be estimated that it will hole through into this station on or about Friday, September 16th.

The TBM, known to the sandhogs as the worm, started its second run (the east tunnel) at a point just south of 92nd Street back in March of this year. Since then it had mined a total of 7,221 linear feet, as of August 31st.

The 485-ton, 450-foot-long machine is now in the process of making a relatively tight westerly curve as it grinds its way towards a stub cavern at the Lexington Avenue/63rd Street station. The stub cavern, shown in the diagram further along in this posting, was built in the late 1970s when this station was original constructed.

The TBM previously mined 7,162 feet of the west tunnel under Second Avenue.

Phase I of the Second Avenue subway (i.e. the extension of Q Line service to the Upper East side) is currently scheduled to be completed in December 2016.



Partial Diagram of Phase I of the Second Avenue Subway
Google Maps
(left-click on the image above for a closer look)
-- The approximate location of the TBM, as of 8/31/11,
is designated with a red cross on the map above.



G3/G4 Tunnels and 72nd Street Station
Second Avenue Subway
(left-click on the image above for a closer look)

This diagram details the current and planned subway tunnels just to the east of the Lexington Avenue/63rd Street station.

The G3 & G4 tunnels (shown above) are being built as part of Phase I of the project. The tunnels designated as S1 & S2, for the future "T Line", will be built during Phase III of the project.

::

Last Reported Location
of the Tunnel Boring Machine
btw. 64th & 65th streets
as of 8/31/11

TBM Run No. 2 (east tunnel)
Tunnel length: 7,789 linear feet (LF)
Start: just south of 92nd Street
End: Lexington Av / 63rd St Station
7,221 LF mined as of 8/31/11
568 LF to run

August TBM Mining Data:
Distance mined: 1,265 linear feet (LF)
TBM mining days: 23
Avg. distance per day: 55 LF


:::::


Here's a listing of the recent additions
to the right-hand column of The Launch Box

"No Subway, but a Little Silence on Second Avenue"
By Michael M. Grynbaum
The New York Times - 8/15/11

"No more underground blasts at night on 2nd Ave" (2:00)
Video
By Jeff Pegues
WABC-TV - 8/15/11

"MTA behind schedule, over budget on two mega projects, feds say"
By Marc Beja
amNew York - 8/22/11

Feds: East Side Access, SAS won’t open until 2018 - 8/22/11
By Benjamin Kabak
2nd. Ave. Sagas - 8/22/11

"Underground Economy: Cashing in on Rubble From the 2nd Avenue Subway" (4:08)
By Ilya Marritz
WNYC - 8/23/11

"A Bonus for First Avenue: It's Not Second"
By Laura Kusisto
The Wall Street Journal - 9/2/11


::


A Footnote:

After four years I've decided that its time to change the layout of this blog. The layout (known as a template) that I selected when I started in 2007 is so old its not even available on the current blogger.com web site today!

I plan to adjust the new template over the next week as I play with all of the new options. In the meantime, please stand by while I rejig the blog a bit.

Ben

Sunday, August 14, 2011

Reporting on the Reports


With this post, I am going to highlight several key reports that have been issued over the past two weeks. These reports are available on the MTA's web site, if you know where to look.

Updates: 8/15/11 & 8/23/11
The MTA has now set a 7 p.m. cutoff time for blasting associated with the new 72nd and 86th street stations. Details have been provided in the updated sections below.



Second Avenue Subway, Phase I Quarterly Report
Report Period: 2Q2011 (April, May, June 2011)
MTA Capital Construction
To find this report on the Internet, follow this path: www.mta.info >
Capital Program > Building the Future >
Second Avenue Subway > Documents

This 29-page report includes a great deal of detail on the project,
as one might expect.

Highlights include:
  • The forecast date for revenue service on the new line under Second Avenue remains December 30th, 2016.
  • The current schedule now includes 67 calendar days of schedule contingency(*). This is a significant reduction in contingency days vs. the 168 day number detailed in the 1Q2011 report. The lost days are primarily due to the five month delay awarding the 86th Street Cavern Mining contract.
  • The contractor mining the 72nd Street Station Cavern has excavated 20,255 BCY (Bank Cubic Yards) [11.9%] to date, of the 170,507 BCY total.
(*) Schedule contingency is "planned extra duration" in the schedule to allow for unexpected delays.

::



Second Avenue Subway (*)
MTA Capital Construction presentation
to the MTA Board of Directors
Capital Program Oversight Committee
July 2011
Location on the Internet: www.mta.info > About the MTA >
Board Materials > 7/25/11 - Capital Program Oversight Committee

Significant critical milestones and issues include:
  • The active lawsuit between Yorkshire Tower residents and the MTA concerning the planned entrances on 86th Street.
  • Delays on the active 96th Street Station contract related to the relocation of utilities.
  • Delay of the award of the 86th Street Cavern Mining contract, by five months, due to the need to obtain a "Buy America Waiver" from the FTA for part of the contact.
The report also includes a detailed Risk Assessment for 86th Street Station Cavern Mining contract.

Additionally, the report includes an interesting 3D view of the planned 86th Street station, shown below:




(*) Note: This 15-page report unfortunately is part of a 161 Mb PDF file on the MTA's web site. It may take some time to load if you click on the link. If the MTA had optimized the PDF file using Adobe Acrobat that could have reduced the file size to just 26 MB.

::



MTA Capital Program Milestones Report - p.38
as of 6/30/11
Location on the Internet: www.mta.info > About the MTA >
Capital Program > Resources > Capital Program Dashboard >
MTA Capital Program Milestones

The timeline consists of six months of historical events and
24 months of planned events.
2010-2014 Capital Program Milestones are tracked using colors: Green: on-time (early or within 0-3 months), Yellow: 4-6 months late, Red: 6 months late.

::



SAS - Contract C4B (72nd St. Station Cavern)
Community Air Monitoring Exceedances: 1/1/11 - 7/12/11
MTA Capital Construction

This report details air monitoring exceedances (dust and total volatile organic compounds) in and around the 72nd Street station cavern mining work zone.

The issue of dust and odors has been a concern for residents near this 72nd Street station work zone for some time. The matter was to be addressed at a special meeting of the Community Board 8 Second Avenue Subway Task Force last week. However, that meeting was cancelled after the MTA sent this letter to Community Board 8.

It is expected that air quality concerns will be discussed at the September meeting of the CB8 SAS Task Force, after the MTA has completed a review and study of the air quality due to the SAS construction activity.


::


Now on to a few other points of interest --



Long-term Construction Look Ahead Map
(Beta version)
MTA Capital Construction

MTA Capital Construction recently launched a new interactive Long-term Construction Look Ahead mapping tool on their web site.

The tool allows a user to view a map of the planned construction-related information for every block within the project corridor - from 63rd Street to 100th Street - on a quarterly basis through the middle of 2013. Information related to the later years of the project will be added in time.

To use the tool, click on the image above and then click on the word "Map" on the MTA's web page. Then click on any of the construction zone icons and a page will appear containing information on construction activities, location, duration of work and traffic restrictions.

You can move the map from left to right by moving the slider bar. You can also select a future period by clicking on one of the blue buttons. (For example, if you click on the Q3 button on the 2012 row, the site will display a map that details the planned construction-information for this period.)


::


MTA Capital Construction awarded the the 86th Street Station Cavern Mining and Heavy Civil Structure Contract, referenced as Contract C-26008, on 8/4/11 to the firm Skanska / Traylor JV. The award amount was $301,860,000, which was the low bid for this contract.


In related news, the MTA issued the following notice of Controlled Blasting for the 86th Street Station Access Shafts.


Blasting Notice - 86th Street Station Cavern Shafts
MTA

The notice says that the contractor will soon start blasting out two access shafts on the east side of Second Avenue at 83rd St Street (the South Shaft) and mid-block between 86th and 87th streets (the North Shaft).

According to the notice, blasting in the South and North Access Shafts (for 86th Street Station cavern) is permitted to take place between 6 a.m. and 12 a.m.
[These times are no longer valid - see the updates below]

Update - 8/15/11
Michael Grynbaum of The New York Times reported this morning, in his article "No Subway, but a Little Silence on Second Avenue", that the MTA has told its contractors that there should be no blasting on Second Avenue after 7 p.m., effective today.

Update - 8/23/11
The MTA just provided me with the following statement regarding the blasting on Second Avenue:

MTA BLASTING NOTICE UPDATE

"In acknowledgement of community concerns related to late night blasting activities associated with the Second Avenue Subway Project, MTA Capital Construction has revised project blasting hours to address the issue.

As of Monday, August 15th, MTA Capital Construction has instructed its contractor that all blasting is to occur prior to 7 p.m. on a regular basis.

The following exceptions will apply:

· Blasting that would affect operations at Memorial Sloan-Kettering/ 64th Street Outpatient Center will be scheduled to occur later in the day to avoid interference with patient care.

· Unforeseen circumstances, limited to instances where there are safety concerns. In those limited instances where post 7 p.m. blasting becomes necessary, an email notification will be sent out to the Community Board, local elected officials and all interested community representatives.

Blasting times in the shaft are from 7 a.m. - 7 p.m., with the two exceptions as noted above.

Blasting for excavation of the shaft at 86th Street will begin in approximately 2 weeks. Blasting for the [86th Street station] cavern will follow excavation of the shaft and we believe that will take place in approximately 2-3 months."


::


And finally a few images --

Here are two images of the work taking place deep inside the the Lexington Avenue/63rd Street station:


Source: Judlau Contracting web site

This would appear to be the out-of-service north side of the station.



Source: Judlau Contracting web site

This would appear to be a view of an unused portion at the east end of the station, under 3rd Avenue.


::



Source:
"The most powerful block in NYC that you’ve never heard of"
Untapped New York - 8/8/11

This image shows a section of the power distribution panel at the New York City Transit Power Control Center. Note the reference to the "future Second Ave. Line".

The designations G3-SB and G4-NB refer to the out-of-service tracks on the north side of the existing 63rd Street / Lexington Avenue station. These tracks will be used when Q Line service is extended to the Upper East Side under Second Avenue.

T1-SB and T2-NB refer to active F Line tracks on the south side of this station.


::


Last Reported Location
of the Tunnel Boring Machine
btw. 69th & 70th streets
as of 7/31/11

TBM Run No. 2 (east tunnel)
Tunnel length: 7,789 linear feet (LF)
Start: just south of 92nd Street
End: Lexington Av / 63rd St Station
5,956 LF mined as of 7/31/11
1,833 LF to run

July TBM Mining Data:
Distance mined: 1,468 linear feet (LF)
TBM mining days: 20
Avg. distance per day: 73.4 LF



:::::


Here's a listing of the recent additions
to the right-hand column of The Launch Box

"2nd Ave. Serenade"
By Danny Gold and Jennifer Fermino
The New York Post - 8/2/11
With over 800,000 views on YouTube, surely just about everyone must have heard of Gary Russo, the 2nd Avenue singing iron worker, by now.

"Second Ave. Concrete Meets Test"
By Allen Houston
Our Town - 8/10/11