Thursday, December 24, 2009
December 24, 2009
Here's a new posting that's just in time for the holidays.
To start with, here's a copy of the MTA's recently released 16-page Quarterly Report for Phase 1 of the Second Avenue Subway project. This particular report covers the period July, August and September 2009.
The MTA should be applauded (yes, applauded!) for their willingness to release reports like this to the public. To the best of my knowledge this is the 1st time that this report has been made available on the MTA's web site.
A complete copy of the report can be found on this link:
3Q2009 Quarterly Report, Second Avenue Subway, Phase 1
The report is full of interesting information about the project, as one might imagine. Here are a few points that I found to be particularly noteworthy:
The report says that Contract 1 is 53% complete (as of 9/30/09) by "invoice construction work" as of 9/30/2009. (This is the same number that the MTA announced at the last meeting of Community Board 8's Second Avenue Subway Task Force.)
So apparently, the MTA calculates how far along they are based on how much of the cost has been invoiced ($200,068,420) vs. the Estimate at Completion (EAC) cost ($377,365,064) for this contract. The "53% complete" number that was given out at the last CB8 SAS Task Force meeting should have been qualified -- since no one would have ever imagined that this how the MTA came up with this percentage. (page 6)
The report goes on to say that the safety record associated with Contract 1 is much lower than comparable figures that are available from the Bureau of Labor Statistics. e.g.. the OSHA recordable incident ratio is 1.92 compared to the industry Average of 4.9. The workers and the contractors on this project deserve a lot of credit for this very good news. (page 7)
And shown below you have a detailed schedule, as of 9/30/2009 (page 13).
(left-click on the image above for a version that is readable)
The report also includes a very detailed budget for the project (shown below). Near the bottom of the budget sheet is a line (highlighted below) that I've never heard anyone talk about before.
Total Project Cost - $4,451,000,000
Estimated Financing Cost - $ 816,614,000
Totals Including Financing Cost - $5,267,614,000
I'd assume that this is the financing cost that is associated with the local share of the project. (i.e. debt service, etc.)
Interestingly, most everyone has been reporting that the total cost of Phase 1 of the Second Avenue Subway is $4.451 Billion -- when in fact the number is actually more like $5.268 Billion. (page 15)
And on page 16 (as shown below) you find a very detailed listing of where all the money for this project is coming from.
- - -
Here are two excellent video reports on the Second Avenue Subway project -- which include a few good quotes from the workers who are making this happen.
" 'This Construction A-Noise Me,' Residents Say" (2:00)
By James de Mellow & Aaron Lee
Columbia University Graduate School of Journalism
ZoomNYC - 12/17/09
"Going Underground" (1:44)
"Chamber 97-1, at 97th Street and 2nd Avenue, will eventually be home to a tunnel as part of the Second Avenue Subway. Carmen Perez and Yepoka Yeebo talked to the engineers and construction workers charged with moving pipes and wires, and making sure the tunnel can hold the weight of an 85,000 lb train."
By Carmen Perez and Yepoka Yeebo
Columbia University Graduate School of Journalism
ZoomNYC - 12/17/09
- - -
On a different, but related topic -- the MTA announced on December 17th that the 1st phase of the Number 7 Line extension has been completed.
The video below shows the 1,000-ton Tunnel Boring Machine (TBM) breaking through the 34th Street station cavern wall.
(NOTE: The video and images below are NOT from the Second Avenue subway project. They are from the MTA's Number 7 Line extension project over on the west side of Manhattan.)
"7 train excavation footage" (1:53)
YouTube - Mayor Bloomberg's Channel - 12/17/09
And here are four images of the TBM, that has been working on the Number 7 Line extinsion, breaking through the rock wall.
Patrick J. Cashin/MTA
Patrick J. Cashin/MTA
Patrick J. Cashin/MTA
Patrick J. Cashin/MTA
These images were posted on Mayor Bloomberg's web site "News from the Blue Room."
You can read the full MTA press release on this link:
"MTA And Mayor Bloomberg Announce Completion Of First Phase Of Number 7 Subway Extension" - MTA 12/21/09
- - -
Here's a listing of the recent additions
to the right-hand column of The Launch Box
Monthly Project Report - Second Avenue Subway
MTA Capital Construction - 12/2009
(a 2-page summary of the project that was prepared for the Capital Construction, Planning and Real Estate Committee of the MTA Board of Directors.)
December 2009 Capital Program Oversight Report
Second Avenue Subway
McKissack + Delcan JV - 12/17/09
(a 12-page independent engineering review of the project that was prepared for the Capital Program Oversight Committee of the MTA Board of Directors.)
Note: This report is part of a very large 61 MB PDF file that is sitting on the MTA's web site. For most people it will take a little time for this to download.
"Second Avenue Subway : Go East, Young Man"
By Dan Fastenberg and Yasmine Guerda
Columbia University Graduate School of Journalism
ZoomNYC - 12/20/09
"Second Ave. station entrance sagas hit 96th St."
2nd Ave. Sagas - 12/22/09
"Subway Construction Blasts Business" (1:38)
Columbia University Graduate School of Journalism
By Dan Lieberman
12/17/08
And, an addition to the glossary
Muck
Happy Holidays!
Ben
Sunday, December 6, 2009
Return of The Gates
btw. 85th & 86th - looking N
The orange construction fencing that is being used to protect the Second Avenue subway work site in the 80s reminds me of The Gates, which was a work of art (by Christo and Jeanne-Claude) that was on display in Central Park back in the winter of 2005.
When I took these pictures, on Sunday December 6th, there were no clouds in the sky and the winter sun to the south had just past the center line of Second Avenue. These conditions provided me with the opportunity to take some wonderful images - with really nice shadows, as you will see.
The Gates - Central Park - 2/05
btw. 85th & 86th - looking SW
85th - NE corner - looking N
It's interesting to see here how the restaurant owner (I assume) has landscaped the construction fence in an effort to improve "the view" from his establishment.
85th - SE corner - looking S
85th - near the SE corner - looking SW
btw. 83rd & 84th - looking S
btw. 83rd & 84th - looking S
83rd - NE corner - looking S
83rd - SE corner - looking S
btw. 82nd & 83rd - looking S
btw. 82nd & 83rd - looking S
btw. 82nd & 83rd - looking N
82nd - NE corner - looking N
82nd - SE corner - looking NW
A jumble of ConEd power lines.
btw. 81st & 82nd - looking N
Various utility lines lines here (and generally between 82nd and 87th Streets) are being relocated in preparation for the construction of the 86th Street station and its entrances.
btw. 72nd & 73rd - looking SW
This is the approximate location of the future 72nd Street access shaft.
Excavation of this shaft, and the one of 69th Street, is scheduled to start in 1Q2010 with controlled blasting [of the shafts] scheduled to start in 2Q2010.
The two shafts will be used during excavation of the station cavern and for muck removal.
btw. 69th & 70th - looking SW
This is the location of the future 69th Street access shaft.
- - -
72nd - looking N (facing 259 East 72nd Street)
This building will be demolished, starting in May 2010, so that the site can be used to construct entrance #2 and ancillary structure #2 for the 72nd Street station.
The ancillary building at this location will be approximately 75 feet tall - which is about 1 story higher than the existing building on this location.
69th - SE corner - looking NW
Ancillary building #1 for the 72nd Street station will be located in the site that is now occupied by the two buildings shown above and the shoe repair shop shown below.
69th - near the SW corner - looking N (facing 235 East 69th)
The plan at the moment is for the new ancillary building to occupy the entire lot, which will mean that some of the windows on the east face of the building at 233 East 69th Street will be covered over by the west face of the new ancillary building. (the red-line in the image above roughly shows the windows that will be lost.)
Needless to say, the effected apartment owners are not happy about losing any of these windows, as Tom Namako of the NY Post reported in his article "Sun block at E. Side co-op" back on September 28th.
Residents of this building turned out en masse at the CB8 Second Avenue Subway Task Force meeting on November 30th to express their concerns.
- - -
96th - looking N
The contractors at this location are laying a new 30 inch gas main in this recently excavated trench.
btw. 96th & 97th - looking NE
New sections of pipe for the gas main are shown here.
97th - looking S
97th - NE corner - looking SW
The old Century Lumber yard building now sits empty. It will be demolished within the next 3 months to make room for ancillary building #2 of the 96th Street station.
(I called the telephone number for Century Lumber earlier today. After a very long delay the phone rang and someone answered. The gentleman on the phone told me that Century Lumber has merged with Mensh Mill & Lumber, which is located in Flushing, Queens.)
- - -
86th - SW corner - looking E
The contractor closed the crosswalk between the SW and SE corners of 86th and 2nd Avenue a few weeks ago so that utility relocation work could take place near the SE corner of the intersection.
Most pedestrians ignored the posted signs (as any New Yorker would expect) and crossed anyway.
86th - NW Corner - looking SE
Another view of pedestrians crossing Second Avenue in a crosswalk that has been closed.
The CB8 Second Avenue Subway Task Force passed a resolution at their last meeting on November 30th requesting that that a person be posted at this location to control the traffic until such time that the crosswalk is re-opened.
Then a few days ago a notice was posted on the web site of the East 86th Street Merchants/Residents Association with the news that this cross walk will be re-opened during the week of December 14th.
- - -
Before I close out this posting I want to return a point that I raised in my posting of December 4th, 2009 - where I wondered how it could be that Contract 1 could actually be 57% complete (a number that the MTA reported to the community at the last CB8 SAS Task Force meeting with this slide.)
Two people wrote to me (one with a comment to the blog and one with an e-mail) to explain this issue to me in more detail.
An anonymous commenter said:
"As someone who works in construction (though not on transportation projects) I actually can believe that Contract is 57% complete.
The reason, I believe, is that the scope of work for Contract 1 is primarily labor.
Building the launch box and shafts at 69th/72nd Streets are jobs that require lots of labor and -- by comparison -- relatively little materials. Boring the tunnels, on the other hand, requires a sizable investment in equipment (the TBM) with a considerable -- but comparatively smaller -- amount of labor.
The scope of work for Contract 1 is primarily labor. Building the launch box and shafts at 69th/72nd Streets are jobs that require lots of labor and -- by comparison -- relatively little materials. Boring the tunnels, on the other hand, requires a sizable investment in equipment (the TBM) with a considerable -- but comparatively smaller -- amount of labor.
It is likely that payment for the TBM itself has already been either partially or fully remanded, because the equipment has probably already been procured and fabricated. Often, boring machines are built specifically for a new project, and it wouldn't be possible to construct a TBM without payment for the people who spend time fabricating it. Although the TBM arrives at the site in pieces, a lot of work takes place before it arrives.
Finally, crews have been working in the 90s to prepare the launch box for years now, representing a massive effort and substantial amount of labor. By comparison, the labor required to create shafts at 69th/72nd Streets is minimal. Although much of the work remaining includes what we'd believe to be the "meat" of this contract (assembling the TBM on-site and drilling the tunnels themselves, then disassembling the TBM), due to the massive amount of labor already exerted it's not hard to believe that nearly 60% of this contract work has been complete."
Ron Aryel, who gave me permission to use his name, said:
"I wanted to help you understand why the MTA said that, as of November, Contract 1 is 57% complete. Your reaction was understandable, but if you look carefully at what's going on, you'll see that it makes sense.
Contract 1 included:
1) Utility relocation at several locations
2) Conventional excavation plus drill and blast to excavate the five block area of the launch box plus access shafts at 72nd St station site;
3) Preparation of the launch box which includes laying electric power especially to power the TBMs;
4) Installation of the TBM, test and boring of tunnel to 72 St.
Of these steps, Step 1 by far requires the most crews, manual labor and time. This was especially so because of the spaghetti (of utility lines) they found underground. Step 2) conventional excavation plus drill and blast, takes far more time and person-hours of work than TBM boring.
The TBM boring gets you the most mileage of tunnel with the least time and fewest people. Once assembled, TBM boring is basically a piece of cake - you turn on the machine and let it chew its way forward. The conveyor belt takes care of the muck; the dump trucks just line up under the hopper and fill up. Yeah, you have to change cutters on the wheel every so often, but there's really not much to do compared to steps 1 and 2. And you make fast progress. It will take probably six months at the most for the TBMs to finish drilling. (South of 72nd st the tunnel will be built as part of Contract 4 of I'm not mistaken.)
The percentage of contract completion is based on how much work (how many tasks) have been completed compared to the total task list for the job. Step 1 above had more tasks than all of the the other steps combined (and likely required more people than the other steps)."
These are good and valid arguments that help to explain how it could be that they are "57% complete" with Contract 1.
By some measurement (like "labor hours worked vs. scheduled labor hours" or "actual work days vs. total work days scheduled") they are 57% complete (with Contract 1) - at the moment.
But I still believe that the public's perception will be different - since the public will assume, with the MTA saying that they are "57% complete with Contract 1" that the contractors are well along with the tunnels - which they haven't even started yet.
Case in point -- this amNY story on December 7th which reported (incorrectly), "tunneling between 63rd and 92nd streets is more than half done, according to MTA materials."
And a just-released report by McKissack+Delcan for the Capital Program Oversight Committee of the MTA Board included this text on page 5-48, "Of further concern is that this contract [SAS Contract 1] is reported over half complete with its main activity, the TBM tunneling of two bores, yet to start."
- - -
Here's a listing of the recent additions
to the right-hand column of The Launch Box
"Second Avenue Strife"
By Elizabeth Wagner
Pavement Pieces - 12/14/09
Arthur L. Carter Journalism Institute - New York University
"43. Because We Keep Digging"
By Christopher Bonanos
New York - 12/13/09
(includes a fantastic picture of the work site under 2nd Avenue)
"The Subway Shaft: How Second Avenue Subway Construction Hurts Businesses in its Path"
Public Advocate for the City of New York - 12/09
(A very well written 17-page report.)
"View-Obstructing Building Takes Shape"
By Dan Rivoli
Out Town - 12/9/09
"Subway Sickness?"
Residents wonder if respiratory problems are linked to construction
By Della Hasselle
Our Town - 12/9/09
"Second Avenue Subway work has caused damage, power loss"
By Heather Haddon
amNY - 12/7/2009
"Small Businesses Seek Hope on 2nd Avenue" (2:00)
By Abigail Wendle
Columbia University Graduate School of Journalism
11/30/09
Sanitary & Topographical Map of the City and Island of New York
1865
If you click on this link and then zoom-in, you can see that much of the TBM launch box site was once marshland along with a a few streams. This might help to explain the instability of some of the older building on Second Avenue.
- - -
All of the pictures shown in were taken on December 6, 2009 unless noted otherwise. The actual posting was loaded onto the blog on Monday 12/14/09.
Friday, December 4, 2009
December 4, 2009
Here are a few notes from the Community Board 8 Second Avenue Subway Task Force meeting that was convened earlier this week, on November 30th.
At the start of the meeting the MTA announced that Contract 1 (for the TBM Launch Box, tunnels from 92nd to 63rd Streets & shafts at 69th and 72nd Streets) is now 57% complete.
They didn't explain how they came up with this percentage, but even a casual observer of this project would have to wonder how they can actually be 57% complete with this contract - when they still have to (a) finish the TBM launch box, (b) assemble the Tunnel Boring Machine [TBM] at the site, (c) bore two tunnels from 92nd to 63rd Streets, and (d) remove the TBM from the site -- all by June 2011 (the current planned completion date for Contract 1.)
The MTA also said that the first two 72nd Street station construction contracts (for building demolition, station cavern mining, and heavy civil work) will be advertised [to potential contracting parties] in December.
S3 Tunnel Constructors said during their part of the presentation that the test blasting program (at the south end of the TBM launch box) was completed successfully during October and that they have now moved to "production" blasting. They expect that the blasting at the launch box site will be completed early in the 2nd quarter of 2010.
Here are 2 pictures, from the presentation, of the work site inside the TBM launch box.
under 92nd - looking SW (my guess)
The pile of rock in this picture gives us the hint as to the photographers location -- since the bedrock that is being removed from the site is only present in the southern end of the work site.
under 94th - looking S (my guess)
If you look carefully you can see the various utility lines that have been hung under the road decking structure above.
In the 2nd quarter of 2010 they expect to start assembling the TBM at the work site and they will also setup the vertical conveyor (referred to by some as a "muck tower") between 92nd and 93rd Streets. The vertical conveyor, which will be used to lift rock from the tunnel boring operation to the surface, will be setup between 92nd and 93rd Streets and it will extend about 25-30 feet above street level.
The TBM will be delivered in 50 truck loads, with 10-15 oversize loads coming in at night.
Assuming that they start boring the first tunnel in July 2010 (my guess) it should take the TBM about 14 months to complete its work. (this assumes that the machine can progress at a rate of about 1 linear block per week, which is what we were told in a previous CB8 SAS meeting.) If you do the math be sure to keep in mind that there are two tunnels, of approximately 30 blocks [each], that need to be bored.
The full 68-page presentation can be found on this link:
Construction Update and Ancillary Facility Design (69th and 72nd Streets)
Community Board 8 Second Avenue Subway Task Force - 11/30/09
- - -
Here's a listing of the recent additions
to the right-hand column of The Launch Box:
"Implementation of the
Metropolitan Transportation Authority's Capital Plan"
Citizens Budget Committee - 10/09
I've added a new section now, with the latest SAS related posting from Benjamin Kabak's New York City Subway blog 2nd Ave. Sagas. Ben has been providing on-going commentary, via his blog, on the Second Avenue subway project since December 2006.
Megaprojects and the Second Ave. Subway
Second Ave. Sagas - 12/2/09
SAS Neighborhood Impact: Station Entrances
Second Ave. Sagas - 12/1/09
SAS Neighborhood Impact: Ventilation Structures
Second Ave. Sagas - 12/1/09
On building subway lines during recessions
Second Ave. Sagas - 11/13/09
Archive with all 90+ Second Ave. Sagas
postings on the Second Avenue Subway
Under News:
"Station Plans Move Forward"
Our Town - 12/3/09
"With new subway, massive eyesores"
The Real Deal - 11/30/09
"Co-op Boards Together vs. MTA"
Habitat Magazine - 11/25/09
"Now it's Second Avenue flood way"
NY Post - 10/30/09
"Bracing for 2nd Ave. Subway"
NY Post - 10/22/09
"Third dig on 2nd Avenue"
Skanska Worldwide - 2009
- - -
A footnote:
I know that I'm way overdue for a posting with a fresh set of pictures. Sorry about the delay, but many other things have been taking up my free time over the past few weeks.
I hope to have a new set of pictures up in a few days - if the weather cooperates this weekend.
Sunday, November 8, 2009
November 8, 2009
Here's a copy of a two-page Second Avenue Subway "Project Update" that was posted on the MTA's web site late last week.
The report is one small part of a 101-page package of material that was prepared for the November meeting of the MTA Board of Directors' Capital Construction, Planning and Real Estate committee meeting.
MTA Chairman and CEO Jay Walder wasted little time with his pledge to start making additional board materials available to the public on the MTA's web site, as part of his effort to make the organization a bit more transparent. One can only applaud these efforts.
(left-click on either image for a version that is readable)
Here are a few items from this report that I think are particular noteworthy:
The Cost for the Design Work:
The MTA has budgeted $ 445,000,000 as the cost to [just] design the Second Avenue subway -- an amount that is effectively 10% of the $4,451,000,000 budget for Phase I of the project. This seems to me like a staggering amount of money for the design and engineering work, but who am I to say ...
72nd Street and 86th Street Station Entrances:
The environmental process was completed for the proposed design changes for these two stations with the issuance of a Finding of No Significant Impact (FONSI) from the Federal Transit Administration. (A copy of the FTA's determination can be found on this link.)
Century Lumber Yard Building:
Demolition of this building, to make way for the construction of an ancillary building for the project, is expect to begin at the end of November. (this building is located on the SW corner of 97th Street and 2nd Avenue.)
Unfunded Budget Amount:
Page 2 of the report shows a budgeted amount of $1.487 Billion for the Second Avenue Subway that has not yet been funded. This amount is part of the MTA's proposed 2010-2014 Capital Program, and all of this amount is scheduled to be provided by "local sources," which I assume means New York State.
As reported on 2nd Ave. Sagas in early October, Governor Paterson has called the MTA's 2010-2014 Capital Program "simply unaffordable given New York’s current fiscal condition." One has to wonder if there is any chance that construction could be held up, or even stopped, because of the current fiscal crisis - which would be just like what happened to the project back in the 1970s.
- - -
In these 3 images the MTA's contractors are continuing their work to stabilize the building on the NE corner of 92nd and 2nd, in preparation for the start of the Controlled Blasting effort. On this day they were installing a piece of steel beam near the top corner of the building.
10/29/09
92nd, btw. 1st and 2nd - looking W
10/29/09
92nd, SE corner - looking N
92nd, SW corner - looking NE
- - -
The Controlled Blasting inside the TBM launch box apparently started this past Wednesday, November 4th, when more than one person in the neighborhood told me that they heard the sound of the warning horns during the day -- but oddly these same people said that they never heard the sound of the actual blast.
It could be that the contractors and the FDNY were just testing the procedures (without the use of explosives) or possibly they were using only a very small amount of explosives, in order to check all of the instrumentation that has been setup on the buildings in the area.
A reliable source has told me they plan to start start with a small amounts of explosives, so as to err on the side of caution. Then as they become more confident they will increase the level of the explosive charges.
- - -
Here's a listing of the recent additions
to the right-hand column of The Launch Box
Construction Creeps Downtown
Impact is worst in East 90s, due to excavations for tunnel boring machine
Our Town - 10/7/09
Second Avenue Business Association (SABA)
a new web link to their site
A copy of the Letter of Interest (LOI) for SAS Contract 4B [C-26007]:
72nd Street Station Station Cavern Mining/Lining & Heavy Civil Work
9/18/09
New Section:
"Historical Information"
with these six links:
Second Avenue Subway Construction in the 1970s
The Launch Box - 9/21/09
"Fallen Transit:
The Loss of Rapid Transit on New York's Second Avenue"
The Third Rail
The 2nd Avenue El
NYCsubway.org
Video: "The 51st State [Episode 24] Transportation in New York:
"The Saga of the 2nd Avenue Subway" (8:00)
Thirteen/WNET - 1975
Video: "The End of the Third Avenue El" - (2:39)
YouTube - 1955
Video: "3rd Ave. El" (10:38)
YouTube - 1954
Sunday, October 25, 2009
October 25, 2009
92nd, SE corner - looking N
(approx. 60' above the street level)
This is a view of the Second Avenue subway work site, in the east 90s, from the roof of the six story building at 1762 Second Avenue. (I owe a big thank you to the owner of Delizia 92 Ristorante & Pizza, who very kindly let me take a few pictures from the roof of his building.)
Two observations:
- It's interesting, from this high angle, to see how relatively "neat and tidy" the contractors are keeping this job site. This is not that usual based on my experience observing construction sites over the years.
- You may notice, from the shadows, that the sun was directly aligned with Second Avenue when I took the roof shots. I did this on purpose because at this time of the year, with the sun low in the southern sky, there is only a period of about 30 minutes when the sun fully illuminates Second Avenue (i.e. without shadows.)
Note that there is no work taking place on the site in these images because it was a Sunday.
92nd, SE corner - looking S
This large hole (which has been officially referred to as a glory hole by the contractors) is used to remove soil and rock from the surface below the decking of the Tunnel Boring Machine (TBM) Launch Box.
It is also sometimes used when the contractors need to lower equipment and material down into the launch box.
Another view of the same hole.
And here is a close up view of the surface at the bottom of the hole, again from the roof.
The left wall in this image is solid bedrock.
93rd - looking S, through a crack in the fence
btw. 93rd & 94th - looking E
(This is a stitched image)
A closer view of the large Liebherr crane that is currently being used (on weekdays) to lift soil from the surface below.
96th - looking S (in the middle of the avenue)
The heavy construction equipment on top of the TBM Launch Box can be seen in the distance.
btw. 95th & 96th
This poster was recently put up on the fence near the project office at this location.
What's interesting to see is that, according to the poster, this project is being funded by the American Recovery and Reinvestment Act of 2009 (ARRA). Until now I wasn't aware that ARRA funds were being used to fund major portions of the Second Avenue subway.
An Update - 11/10/09
I asked the MTA for further details regarding the use of ARRA funds to build the new SAS 96th Street station, and here's what they told me in an e-mail reply:
QUOTE
The MTA will use funds provided through the American Recovery and Reinvestment Act of 2009 (ARRA) - in combination with other federal and local funds - to construct the SAS 96th Street Station. The grant for this work has not yet been executed and therefore is not included on the list for ARRA grants for New York County at this time. The sign stating that the project is funded through ARRA is posted at the work site because the MTA is using a federal provision called "pre-award authority." This provision allows the MTA to use local funds to advance the project in anticipation of receipt of the federal grant.
UNQUOTE
- - -
Tom Namako reported the other day, in this New York Post article, that the MTA is spending upwards of $500,000 to shore up the 6 story building at 1776-1778 Second Avenue, on the NE corner of 92nd and Second. (This is the building that the NYC Department of Buildings evacuated back in late June because it was in danger of collapse.)
According to the article, the MTA agreed to pay for the work to stabilize the building rather than run the risk of having the subway project delayed any further. (the controlled blasting in the southern end of the launch box has been delayed because of the stability of this, and one other building, on Second Avenue.)
The MTA's contractor, S3 Tunnel Constructors, has been working hard to quickly set up a network of bracing, on portions of the outside and inside of this building, over the past few weeks. I can only imagine what it must look like inside, since the MTA has said that their only objective is to stabilize building so they can move forward with the blasting in the launch box.
btw. 92nd and 93rd - looking SE
A view of the building in question, partially covered with scaffolding. The portable crane shown is being used to lift sections of the steel bracing up to the workers on the scaffolding.
- - -
92nd, NE corner - on the SAS project Bulletin Board
This notice announces that Controlled Blasting is scheduled to begin during the week of November 2, 2009.
Oddly, I was unable to find any other copies posted in the neighborhood, as of today. I would have thought that a notice like this would be posted through out the area, so that as many people as possible would know what is going in.
But I did though find a copy on the MTA's Second Avenue Subway Construction Look Ahead web page -- and here's what it says:
QUOTE
The Second Avenue Subway project will be using a well established excavation technique called controlled blasting to facilitate the excavation of the Tunnel Boring Machine Launch Box. We have used this technique at many of our projects in Manhattan.
Controlled blasting activities are scheduled to begin
the week of November 2, 2009.
The Fire Department of New York (FDNY) has approved a controlled blasting plan for the area of Second Avenue between 91st and 93rd Street which will be carried out in coordination with the MTA and S3 Tunnel Constructors. All blasting will be conducted under the direction and regulations of the FDNY. Blasting is permitted to take place during the approved Second Ave Subway working hours of 7 AM to 10 PM, although, every effort will be made to limit blasting to daylight hours.
Blasting Procedures
* All pedestrian and vehicle traffic will be temporarily stopped during each blast occurrence. Blasting will occur approximately 4 to 5 times daily, with each blast lasting no more than one minute.
* There will be a warning whistle before each blast
1 whistle as a warning sound
2 whistles indicate the blast is imminent
3 whistles indicate the blast is complete and all is clear.
* Flagging personnel will be positioned at the north, south, east and west corners of the blast zone to inform and direct pedestrians.
* Signs will be posted around the work site that will state:
* DANGER BLASTING - NO RADIO TRANSMITTING
As required by New York State regulations, and monitored by FDNY, all explosive materials are delivered to and from the work site daily.
Vibration and noise limits have been established by the MTA and the project designer. The vibration and noise readings will be monitored by the construction management team.
Please direct any questions or concerns to Marcus Book, Assistant Director, MTA NYC Transit Government and Community Relations at 646-252-2675 or Claudia Wilson at the work site at 212-792-9716.
UNQUOTE
Two notes about the blasting:
I saw members of the FDNY Explosives Unit at the work site last week -- so clearly they are getting ready to start blasting soon.
A FDNY Blasting Permit has not yet been posted on the SAS project bulletin board at 93rd & 2nd, as of Sunday 10/25/09.
An Update -- 11/10/2009:
I have been told by the MTA that the contractors have not posted the FDNY blasting permit at the site because there is no requirement to do so.
- - -
In other news, the MTA recently announced on their web site that the following two Second Avenue subway contracts will be advertised (to potential bidders) in December 2009.
Contract 4A [C-26014]
72nd Street Station
Demolition of Existing Building and Relocation of Utilities
Contract 4B [C-26007]
72nd Street Station
Station Cavern Mining/Lining & Heavy Civil Work
- - -
And lastly, here are a few pictures that I took of the work site using an Optrixx prism lens that I purchased over the weekend at Sam Flax on 3rd Avenue.
Under the scaffolding near 92nd and Second
Near the Bagel Express deli
The rear end of a Liebherr crane
A side view of the same machine
Subscribe to:
Posts (Atom)