Sunday, June 24, 2007

June 24, 2007


91st Street, NE corner - looking north
Removal of the old sidewalk continues.



btw. 92nd and 93rd streets on the east side of 2nd Avenue - looking north



bts. 92nd and 93rd streets on the east side of 2nd Avenue - looking south
The fire hydrant that used to be near the curb has been moved back to within about 2' of the building.



93rd Street, NE corner - looking north


btw. 93rd and 94th streets on the east side of the street - looking NW
The sidewalk has been removed and crews are preparing to add a new traffic lane on the east side of 2nd Avenue - where half of the sidewalk and the old curb used to be. After this is done there will be a 6' wide sidewalk, a Jersey Barrier, and a new traffic lane. This lane will be used for traffic M-F but will be available for parking on the weekends and holidays.

Saturday, June 16, 2007

June 16, 2007


92nd Street, SE corner - looking south
Crews now start to remove the sidewalk.



94th Street, near the SW corner - looking southeast
A machine for cutting the street sits waiting.



94th Street, near the SW corner - looking NE
Two crews work on moving the lines for the traffic signals.



94th Street, SE corner - looking west
A crew continues their work on the lines for the traffic signals.



92nd Street, near the SE corner - looking south
A crew cuts the sidewalk open with a (very loud) saw.